Tank Flush, Esperance WA

NPE were engaged by Carey MC to provide Dewatering and Environmental Management for the Berth 2 hardstand renewal, construction of flush tanks and installation of a dissolved metal treatment filter system at Southern Ports’ Port of Esperance.

NPE began with the development of the Dewatering Management Plan to align with the conditions required by the Southern Ports Authority.

After strict security checks (MSIC) and inductions NPE mobilised the personnel, drilling equipment and dewatering equipment to the Esperance Port on the 23rd of January.

The Guys on site did a great job drilling 5 production bores, 1 x monitoring well and installing the pumps, generators, flow meters and the poly ring main. They operated on a very tight time frame which allowed Carey MC to return to the original schedule after losing time during the piling due to difficult ground conditions.

NPE achieved the adequate draw down which allowed Carey MC to excavate down to invert. The concrete blinding has been poured and the first base slab is due to be poured in the coming days. The excavation ( supported by sheet piles) is approximately 12m x 14m x 7m deep. The current groundwater draw down is around 5m allowing sufficient compaction and dry working conditions.

NPE Continue to monitor the dewatering and environmental quality with weekly lab samples and on site testing every other day. The dewatering is scheduled to run for a total of 10-12 weeks.

The personnel on site have received great feedback from Carey MC.

High-Performance Pumping Solutions for Extreme Weather Events- QLD

Quarry pit dewatering is essential for maintaining safe and productive operations by removing accumulated rainwater and groundwater to prevent flooding…

Assisted Water Reduction Using Evaporation Fans in Queensland

Our client required a 24-unit evaporator fan package at Cannington Mine to lower water levels within the Tailings Storage Facility…

 NPE Bypass Solutions for  Black Rock Water Reclamation Plant

 National Pump & Energy (NPE) was engaged by AMH Civil to deliver a full bypass solution for the Black Rock…

Wet Season Management in North-West Queensland Mining​

NPE was engaged to support a remote north-west Queensland operation following significant rainfall, with approximately 370 mm recorded over a…

Royal Far West Manly Dewatering

NPE was awarded a dewatering and water treatment project to facilitate construction activities. To manage this project effectively, the temporary…

PFAS Treatment Perth, WA

The treatment process begins with a dewatering system that extracts groundwater for processing. The influent is conveyed through the plant,…

Critical Sewer Bypass Solution with Dual Diesel Pump System

National Pump & Energy (NPE) was engaged to support a critical infrastructure project with a temporary sewer bypass solution. The…