Port August Bypass, South Australia
The local water authority in South Australia had some major works with one of their pumping stations which required the system to be off-line for approximately 2 weeks.
Being a critical station in the sewer network, NPE were engaged by their contractor to undertake temporary sewer bypass works which entailed diverting the raw sewerage around the pumping chamber to allow these works to be undertaken.
Based on the existing pumping systems capabilities, suitably sized, solids handling Rental Pumps were selected by NPE to ensure the maximum flows could be handled to prevent any back-up of the system or potential overflows.
Our NPE Service/Operations Team installed the pumps and pipework as required by the client to ensure timeframes were met and a seamless change over.
Our pumping system was installed complete with a telemetry system, enabling the pump performance to be remotely monitored and to alert our Service Team of an issue if it were to occur.
The temporary rental bypass ran without issue, allowing the client to undertake their scope of works and reinstate the refurbished pumping system.
Once completed, our system was dismantled and demobilised.
Onsite Ammonia Treatment and Discharge Enablement – Newcastle
National Pump & Energy (NPE) were engaged to address elevated ammonia levels in a client’s storm water retention pond after…
Engineering Meets Expertise: NPE Partnered with Nacap on a Remote Wind Farm
National Pump & Energy (NPE), in partnership with Nacap, delivered an innovative water management solution for a remote wind farm…
High-Performance Quarry Pumping Solutions for Extreme Weather Events- QLD
National Pump and Energy (NPE) are the industry-leading Water Management and Treatment Solutions experts. Offering Dewatering, Bypass Pumping, Pump Hire…
Wastewater Treatment Plant – Digester Cleaning in South Australia
NPE was engaged by Fulton Hogan to undertake the full cleaning of Digester #6 at the Bolivar Wastewater Treatment Plant…
Huntingdale Sewer Infrastructure Dewatering Project
Huntingdale Sewer Infrastructure Dewatering Project – Case Study The Huntingdale dewatering project involved installing more than 1.2 km of new…
NPE Bypass Solutions for Black Rock Water Reclamation Plant
National Pump & Energy (NPE) was engaged by AMH Civil to deliver a full bypass solution for the Black Rock…
Wet Season Management in North-West Queensland Mining
NPE supported a remote north‑west Queensland site after heavy rainfall, with 370 mm recorded in seven days. The rain temporarily…




